Certainly.
In our first audit we raised a concern about “construction-ready”, about the fact that the government quite understandably was relying on other parties to state that projects were ready to go. We raised the risk that some weren't, and there could be delays. So the government in all of those programs undertook timely monitoring, good reporting, and in many cases, when projects appeared to be slipping, they took corrective action. In some cases they took the money and put it into other projects that could be completed in time.