We made one very specific recommendation about preparing and presenting the full costing information, and they accepted that. On our assessment of whether due diligence was applied, we felt that National Defence did not apply sufficient due diligence and that Public Works should have provided more oversight. Those were the conclusions they disagreed with.
We put the statement in the report that the departments disagreed with our conclusions because it was out of the ordinary to have that type of response from departments. We felt it was important to make it clear to people that we looked at the evidence, came up with our conclusions, published our conclusions, and the departments disagreed with the conclusions.