Thanks.
I'm going to switch over to Public Works, please.
I want to give you an example. I have an order paper here, and this is only one of four we've put.... This one is about 500 pages, listing all of the contracts given out to various consulting firms. This one is Deloitte. I'm looking at three dates, a week apart, each one worth $72,000 for scene security and event security services. Basically, Deloitte was hired three separate times to see if the contract was awarded fairly and in a transparent manner. It's a quarter of a million dollars, repeating the same item three times in a row.
Do you find that justified, PSPC?