Public Accounts committee  My answer to that would be somewhat similar to what you've heard already. Where sensitive documents are identified, we apply--

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  I would not make any slur whatsoever against the engineers and contractors involved in this job, in that they did follow the rules that were established.

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  However, it is standard practice in the architectural, engineering, and construction industry that when unclassified documents are to be disposed of, frankly they're put in the garbage. In this particular case they were put in a garbage receptacle. Somehow they appeared in the mi

June 3rd, 2008Committee meeting

Ross Nicholls

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  --relying on the review that's being carried out by the department to identify--

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  They were under the control of the contractors we engaged.

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  We have a role. I don't think it makes a lot of sense to launch an independent investigation at the same time that the department is reviewing the situation.

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  Obviously I would have preferred not to have found out about it in the same way that others did, by reading the newspaper. However, immediately upon finding out that they weren't classified documents, we go back to the question of what the proper practice is, what the appropriate

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  Mr. Chairman, honourable members, I am pleased to appear before you again. At the last Public Accounts Committee meeting I explained DCC's role as contracting authority for DND infrastructure projects and how DCC is accountable for taking the measures necessary to protect the sen

June 3rd, 2008Committee meeting

Ross Nicholls

Public Accounts committee  No. We have now signed an agreement with—

February 26th, 2008Committee meeting

Ross Nicholls

Public Accounts committee  Since 1986, when the policy was around. However—

February 26th, 2008Committee meeting

Ross Nicholls

February 26th, 2008Committee meeting

Ross Nicholls

Public Accounts committee  To clarify, we've entered into the formal agreement with Treasury Board since the audit. Prior to that time, we always implemented the measures required by the government security—

February 26th, 2008Committee meeting

Ross Nicholls

Public Accounts committee  Sir, I suggest that you look back, and you will not find a situation where we have not complied.