All right. Let me move on to another one.
DND's departmental performance report, tabled on the same day as the supplementary estimates (B) in November of this year, noted that a little more than half, 54.5%, of the Canada First defence strategy projects are on time. When you look at the joint and common support projects, none of them are on schedule despite a target of 85%.
Let me give you an example. The percentage of joint and common support projects on schedule is zero; the percentage of aerospace projects on schedule, 55%; the percentage of land projects on schedule, 43.5%; and the percentage of maritime projects on schedule, 57%.
Mr. Fadden, I wonder if you can explain why we haven't been able to achieve the projected 85% and to what extent the $652 million that DND is requesting will help the government meet its own target with regard to the acquisition of equipment and materiel in accordance with this defence strategy.