Thank you for that. I appreciate that answer.
Mr. Nussbaum told this committee that the barn came in under budget at $8 million. He said the budget authority was $8.6 million, with about $1 million in contingency risk.
I am not going to ask you this question, because I know the answer based on the other two.
My third question is for the Auditor General, as well.
We submitted a list of more than 30 questions to the NCC for written responses that representatives from Treasury Board and Public Works and Procurement were not able to answer. They told us to ask the NCC for answers. They told us the NCC is a Crown corporation that can act like a private company, with added flexibility in how it awards contracts. We asked about the number of contracts, including millions for a construction manager and subcontracts that were sole-sourced. We are now awaiting the NCC's response.
Do you recall whether that special 2017 audit recommended that the National Capital Commission spend $8 million on a barn?