It's under section 73, and the three-year permits can be either for research for the benefit of the species or for incidental effects. It means that if there is incidental harm or mortality to the odd individual, it's allowed, provided a series of conditions are approved.
Some of our colleagues--not BC Hydro but other power companies in B.C.--have applied for those, and they've been unable to obtain them so far. So as far as I know, there are no current permits. The hydroelectric industry is basically, in terms of not having permits, out of compliance right now. We at BC Hydro have been working for three years to try to get into compliance.