Evidence of meeting #54 for Environment and Sustainable Development in the 45th Parliament, 1st session. (The original version is on Parliament’s site, as are the minutes.) The winning word was storage.

A recording is available from Parliament.

On the agenda

Members speaking

Before the committee

Bouchard  Vice-President, Public Policy and Regulatory Affairs, Deep Sky
Amil Shapka  Co-founder, No CO2 Pipelines Alberta
Guyon  Analyst, Climate-Energy, Nature Québec
Nickel  President and Chief Executive Officer, Petroleum Technology Research Centre
Letourneau  President and Chief Executive Officer, Svante Technologies

Patrick Bonin Bloc Repentigny, QC

Thank you, Madam Chair.

Mr. Shapka, you mentioned water and health risks and issues related to earthquakes. In your view, are there any other significant risks that we should be aware of? Could you possibly send the committee a document explaining your concerns or documentation on those risks?

4:25 p.m.

Co-founder, No CO2 Pipelines Alberta

Amil Shapka

Yes, I'll gladly do that.

Patrick Bonin Bloc Repentigny, QC

Thank you.

You mentioned a request for an impact assessment that was made to the minister. Can you also submit the letter that has remained unanswered, as I understand it, since last March?

4:25 p.m.

Co-founder, No CO2 Pipelines Alberta

Dr. Amil Shapka

Yes, I'm happy to do that also.

Patrick Bonin Bloc Repentigny, QC

Okay, thank you.

Mr. Bouchard, thank you for being here.

One question remains. Do you think that we can continue to expand oil and gas production in the country and that, using your technology, we'll solve the problem by capturing CO2? Could it handle that expansion?

4:25 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

I won't get into the political debate. As I said earlier, our position is that we need to turn off the tap and empty the bathtub. The faster we do the first one, the faster we'll meet climate objectives.

Patrick Bonin Bloc Repentigny, QC

When you talk about turning off the tap, what do you mean?

4:25 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

I mean stopping emissions as quickly as possible.

Patrick Bonin Bloc Repentigny, QC

Thank you.

There are still financial issues. The government has only so much money. There's always a debate when it comes to determining how much to invest in developing carbon capture and storage technologies in order to perhaps lower costs, compared to the option of reducing emissions immediately, which also takes energy.

What do you think is the balance that needs to be struck?

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

There is indeed a trade-off. The technology is still being developed, so we don't need to put all the electricity into direct air capture of carbon at this time. In any case, we don't have the technology to deploy it at scale.

What we are seeing is a curve that will evolve gradually. For example, in Quebec's integrated energy resource management plan, the idea is to deploy between seven million and eight million in carbon capture and storage capacity by 2050. Obviously, it won't be done overnight; it has to be done gradually.

Patrick Bonin Bloc Repentigny, QC

When you talk about seven million to eight million, what exactly do you mean?

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

It's between seven million and eight million tonnes a year. I'm sorry, I forgot to specify that it's tonnes.

We're talking about a capacity of seven million to eight million tonnes a year. It will be done gradually. I see it as a bit of an exponential curve: We're going to start slowly, we're going to learn to do it properly and safely and, gradually, we're going to deploy the capacity up until 2050.

Patrick Bonin Bloc Repentigny, QC

Thank you.

The Chair Liberal Shannon Miedema

Thank you.

Mr. Leslie, it's over to you for five minutes.

4:30 p.m.

Conservative

Branden Leslie Conservative Portage—Lisgar, MB

Thank you, Madam Chair.

I'll start with Mr. Bouchard.

How has Deep Sky managed to be so successful with more or less only private investors when everybody else seems to be very reliant on federal or provincial money?

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

We're basically de-risking the technology for investors. In most cases, companies will rely on their own single technology. If that technology doesn't work, investors are out of luck and the company is out of business.

As I said earlier, we have five technologies deployed right now in Alberta. We have three more coming. We have technologies from large companies and from start-ups, and we're iterating with our technology providers.

4:30 p.m.

Conservative

Branden Leslie Conservative Portage—Lisgar, MB

Your company aside, when we look at the whole of this industry, if it's too risky for private investors, why should taxpayers be the ones we continuously look to as the major funders of these projects?

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

I can't speak for the rest of the industry. I think the industry has to assume part of the risk. That's the way we're doing it, and I think we can be a model for others so that it can be developed.

We're going to need some public money. I'm not going to pretend that's not the case. This is an emerging industry, and it's the same case for every emerging industry. We need some public capital to get it going, to de-risk some of the investments and then to scale it up and allow the private sector to fully fund it.

4:30 p.m.

Conservative

Branden Leslie Conservative Portage—Lisgar, MB

My understanding is that you've worked in government in the past. I'm curious. At the time that changes were made to the Impact Assessment Act, why were CCUS projects never automatically designated for an impact assessment review?

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

I can't answer that. I don't know.

4:30 p.m.

Conservative

Branden Leslie Conservative Portage—Lisgar, MB

It just seems strange. I tried to look through the history to find out if it was part of the recent regulatory pullback of interprovincial and other elements from the review process, but it seems as though this was never included.

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

That's my understanding, but I don't know why.

4:30 p.m.

Conservative

Branden Leslie Conservative Portage—Lisgar, MB

That's fair enough.

Should projects of at least a certain scale go under some sort of.... I understand the Alberta regulator said they don't, and it reserves the right to, in future, put forward a necessity for projects to go under review. I assume that's if you or others expand the scope of your projects.

When I look at Pathways, the scale of it is massive. Should a project of that scale go through a formal impact assessment, whether it is federal or at least provincial? I would suggest it should be federal.

4:30 p.m.

Vice-President, Public Policy and Regulatory Affairs, Deep Sky

Mathieu Bouchard

You have the agreements now between Ottawa and the provinces on project assessment. In Quebec—I'm more familiar with that situation—there are going to be thresholds, and it's going to be subject to a full impact assessment above a certain threshold. Alberta makes its own choices. I'm not as familiar with Alberta.

Branden Leslie Conservative Portage—Lisgar, MB

In the case of Quebec, do you know if they are basing it on a tonnage threshold? What is the threshold they're looking at?