First of all, it's much higher than 90% in Quebec. Secondly, on the EA process, if you're developing a project worth $6 billion, there's probably $1 billion of interest in there. You're probably spending $300 million to $500 million on the environmental studies, consultations, and engineering required just to get through the whole process.