On the point of accelerated capital cost allowance, I'm not sure that governments have given the industry what they've asked for on that front. As my colleague mentioned earlier, it takes a long time for companies to get approvals, do the engineering, order the equipment, prepare the site, do foundation work, do mechanical construction, get the equipment delivered, get it installed, and get it commissioned, at which point the ACCA starts to kick in. That takes much, much longer, in general, than two years. It's more like five years. It's those kinds of activities that I think we want to encourage in this country. I think it's those kinds of activities, those major modernizations, that improve productivity, that improve the environment—