I don't have the report in front of me. It might be a better question to pose to Infrastructure Canada. I could say that is something you normally see with infrastructure programming and infrastructure funding. Very often there are delays either in reaching agreements with provinces to commit funds to specific projects or, if you're dealing with large complex projects, in the environmental assessment front-end design phase as well as in project execution.
I think a good example is the way in which funds under the 2007 Building Canada plan are being used to pay for the Ottawa light-rail project. As you're aware, the final agreements with the proponent for that project were signed this year.