Thank you, both.
Mr. Fréchette, I have a question on infrastructure.
What seems to be a perpetual problem with infrastructure programs, whether it is due to federal, provincial, or municipal government, is the late start for infrastructure start-up. The fact of the matter is we are in June. You don't think you have anything done on this, but maybe you could consider it when you are doing your infrastructure study. What is the impact on the overall investment, and the costs actually, when tenders are not released in March for infrastructure programs that are coming in the summer?
I am told by the municipalities that if they don't get started until July, their costs go up because there is less labour availability, etc. Therefore, the taxpayer doesn't get the benefit of the full infrastructure program.
I am just suggesting that maybe you could look at that, as you think you are going to do some infrastructure work later. Is that right?