The headline rates are 50% ITC for carbon capture, 37.5% for carbon capture pipelines and, I think, 60% for direct air capture, and they are generous. They compare with what's available in other jurisdictions.
The challenge is that there are a lot of details in the legislation that may make it hard to achieve those headline rates. If projects were delayed beyond 2030, or if we can't get equipment installed and we buy it at one rate and install it at another rate, etc., then there's development versus refurbishment. You can only claim 10% of refurbishment expenses compared to development expenses. There are a lot of details that may make it hard to achieve that 50% rate on the capital deployed.