Thank you, Mr. Chair.
Thank you for appearing.
We may have some questions about enforcement as we go; be prepared for those as well, but let me follow up on a few things on this gravel extraction first.
The CEAA evaluations that are done, would they have been done...? It seems to me one of the key components of this whole enterprise would be how you're going to get from the bank to the gravel bar. So would the CEAA evaluations have been done with the notion that this causeway was going to be used to get out there, or was some other method of getting over to the gravel bar considered?