I'm happy to comment on that.
We've been through two processes. The first was our initial work in 2009-10. We did the design work and then sized the equipment and got quotes from the supplying industry. We have now raised the money to build the farm. We now have firm quotes because we have construction drawings. We're about to go. We very much know the true cost of what we want to build.
The process that DFO went through was a different process. It was a collective process of advised inputs from the industry and many of those numbers, to my belief—and I was part of that process—were not supported by quoted numbers.
I'm not surprised that there's a difference. The proof is in the pudding, so to speak: go build one and add up the numbers. That's exactly what we're doing.