The first one is well under way. The construction on the second one will start shortly. They will be building the ships in parallel. They don't have to work one at a time.
There are some interim milestones that we're paying attention to. I wouldn't say they're hitting all of them, but we're in discussion with the shipyard about the delivery of all three vessels by December 2017, which is their contractual commitment, and whether there will be any slippage on that. I don't have a conclusive answer for you today. The yard is working to keep those three ships on schedule.