I don't know where that number has come from.
Within the project budget, because this was a national project started in 2012, we estimated a one-time cost of $50,000 per employee for relocation.
There is equipment in Comox, but that's the banks of servers, the racks of computer equipment needed to power the back end. That's not the front-end modules, computers, and so on, that our operators use. They are in Victoria now.
As far as the relocation of employees, there's a fixed cost for that across government and we've applied that within the project.