Mr. Hutchinson, in a recent news article, Seaspan stated that the three offshore fisheries science vessels are 90%, 60%, and 40% complete. Since it now appears that these delivery dates are no longer considered secret or under commercial confidence, can you please provide this committee with a report, by the end of this week, with the precise dates as currently stated on each vessel's build schedule?
On March 20th, 2018. See this statement in context.