Thank you so very much. Haishka.
I want to turn to our engineer with the Kiewit Corporation.
Mr. Tones, I know that you've been a recipient of $17 million initially, and that the cost has skyrocketed to $52 million. I'm wondering. Is the mandate—the terms of work, the scope of work that your company has right now—restricted to removal of rock? Or is any portion of it designated for how now is the time to start figuring out how to build fishways?
I hear you, Chief Harry. We don't want to abandon getting the rock out of the river, but it seems to me that we had better start figuring out how to build those fishways, because it's urgent.
What does your contract ask you to do?