If I could jump in, I think the RFP was issued around 2000, and there were three main ERP vendors that they were considering. They put together a special office, a central office with an ADM in charge, to run the implementation across all the ministries and stage the various ministries in, because you didn't put 25 ministries on at once. They were staged in over a three-year period.
They started being staged in during 2001. They picked the system, they brought the consultants in. They had to make some hard decisions, because as I think somebody indicated, every different ministry came back and said they wanted to customize the system. They were very tough about saying no customization. The first ministry started going on around 2002, and it took about three years to get them all on.