I was made aware by Minister Baird that he had received a copy of the contract. I indicated to him that we would do a legal assessment to determine whether delaying the decision would result in the project costs going up. We made a determination that the decision could be delayed up to December 15 without incurring additional costs. That information was relayed to the city in my letter of October 10. So I was informed by the president that he had received a copy of the contract, and we proceeded on that basis.
On February 26th, 2008. See this statement in context.