Just one question, Minister, and thank you for your time.
It wasn't just the city that said there would be major implications to delaying the contract. Contradicting your own version and take on the contract, it was also Siemens. I'll table with this committee a document dated Tuesday, October 3, 2006, wherein Siemens details the key messages of a meeting they had with you when they detailed the major cost implications of a delay.
But I want to know specifically what rights you or the federal government had under the contract to invoke the clause 6.1.7, which is the one you use. What rights did you or the federal government have to use that clause to extend the closing dates for the contract between the City of Ottawa and Siemens?