Thank you.
I'm pleased to be here to ask you some questions, Minister.
I'm going to ask questions about the Victoria in-service support contract. My understanding is that Treasury Board was asked for about $1.5 billion for the total contract. And it's divided into three levels: level one maintenance; level two maintenance; and level three maintenance, extended dock and work period major submarine overhauls and refits.
The puzzling thing is, although it's a $1.5 billion contract, only $57 million has gone to tender. That's 4% of the contract; 96% is not tendered. I wonder, did the original tender include only the first level of maintenance, the second level...? I don't believe it could have included the third level of maintenance in the program. What did the first tender include?