The timing for completion is June to August 2008 when everybody will be in that building, and we're still on course to be ready for that particular asset.
Once that building is empty, the campus itself, we will be looking at various reuses for that existing campus in the Alta Vista area. If you look at where it's situated right now, the one thing the RCMP was most pleased with is the fact that it takes that highly secured facility out of a residential area. If you see where the current RCMP headquarters is, it abuts right up to a residential neighbourhood in Alta Vista, and based on the new security requirements and in conjunction with agreements with their U.S. counterparts, they needed to have a facility that provided a 100-metre setback from any roads. This existing facility of JDS provides that heightened security as well.