What we provided him today is a list of all the stimulus projects approved, where they are, what the project is, the cost of the project, and the federal-provincial contributions.
Sorry, I'll get to your answer. What we've indicated to him is that this is the first cycle of claims under a brand-new program on 3,000 projects, so we're going back with the provinces and territories and reviewing the information they provided, clarifying it. They have questions, we have questions, so as that data is verified and accurate and complete, we will then be providing it to him over the coming weeks--on the claim information that's provided.
We've given him a complete data set on all the projects and we've done that within 37 days of his request. I would point out that other requests responded to, to him, range anywhere from 25 days to 125 days, and the rest of the--