Madam Chair, yes, that is what we're concerned.... You see, sole-source contracts or directed contracts are considered high risk in principle, and the risk mitigation strategy that the government has is that it gives lower levels of authority to government officials. You have to go to Treasury Board or senior management to get approvals.
Now, just because you've gone to the market.... And you've improved transparency, no question about it, but confirmed is only one supplier. You know, your authorities go up....
Let me just apologize for a minute for not explaining that in addition to the annual report, we've produced five detailed reports. I would really recommend you, sir, to look at them, because in the case of Public Works, for goods, the authority goes from $2 million to $40 million.