Thank you very much.
Again, thank you for your candour today. I would love to be able to provide you the departmental analysis on the submission that was made for the $100 million, but we don't have it. We do have it for other submissions, but not for this particular one. So I'll simply say that.
We do have the executive summary, if I can use that term, that does talk about the project developer being Green Rite Solutions, an Ontario corporation, and that the project proponent will build and operate eleven different facilities located in municipalities across the country. They went so far as to use your company to say they were going to do all this manufacturing, build these eleven facilities.
I find it unusual—and I'd like your perspective on it—that the Government of Canada, through this access that they gave Jaffer's company to submit this proposal, didn't do due diligence to actually talk to anyone in your company.
We do have e-mails that went to a Mr. Jerry McLeod of your company, but that's the only connection.