Well, to be fair, I didn't look. The thing is, I didn't know the program existed, but my meeting took place on June 16, so that was about two weeks after it was announced. I did a search after the fact and I think it was announced up north at the end of May. Subsequently, I didn't bother going and looking, because in my view an infrastructure program historically is one-third, one-third, and one-third, and they may introduce a private sector component.
But the whole thing just didn't make any sense, because you're not going to be able to build a facility with federal dollars in Ontario and hook up to the grid unless the Ontario Power Authority gives you the proper approvals, and that's about a two-and-a-half- to three-year process.