That's it. It's an interesting fact.
I want to turn to Public Works. I said I had four questions to ask in five minutes, so thank you for pointing that out.
Item 168 on the spreadsheet is the fit-up of the quarry site near Huntsville for the RCMP. We understand or have been told that the government actually had to pay to have that site levelled not once, but twice. I want to know why the second levelling was necessary and what the additional cost to the government was of that second levelling. Again, I understand that the improvements to the site were dug up and obliterated after the G-8. Why was that additional cost incurred?
If you could be brief, I'd really appreciate it.