Yes, I can. I'm sorry for my hesitation.
You mean differences in terms of the P3. Quite clearly, this project would never have gone ahead in the first place had it not been for a number of different factors. I may have alluded in my presentation to the fact that the Abbotsford Regional Hospital and Cancer Centre, prior to 2003, was actually designed and ready to build. In terms of design, it was ready to go for 18 years. It was only when the cancer agency joined in partnership with Fraser Health, which runs 16 hospitals in British Columbia, that this actually started to gain traction with the Ministry of Health.
Furthermore, the project would never have been constructed at all were it not for the proposal's going through a PPP process.