You'll recall that I came and spoke about this contract two years ago. The reason why the contract was terminated at the time was simple. The general contractor who won the invitation to tender was unable to meet the objectives of the contract quickly enough. Therefore, PWGSC withdrew the contract because the contractor was not meeting his obligations. We contacted the surety company, which completed the work.
It was mainly a matter of non-compliance. The contractor's work was unsatisfactory. That's why we terminated the contract at the time.