As we said, we had an initial idea for West Block in 1997, but it was really very preliminary.
Around 2000, the project was stopped because of the millennium festivities. So that slowed the work down.
Then, there were a lot of discussions between the various partners to find out what direction should be taken. A lot of discussions took place between 2000 and 2005, and agreements were not necessarily a priority.
In 2005-2006, we drafted a report with our partners, and the report made a long-term vision possible; that started in 2007.
There were a lot of negotiations before decisions were made. Those decisions were transformed into contracts. As I said earlier, walk along Wellington Street and you will see that things are moving forward.