The restoration of the West Block is on budget and on schedule. The project is progressing nicely.
If you take a look at the figures you mentioned a moment ago, you will notice that we spent $44 million more than planned last year. But that was not a cost overrun. It was simply a matter of the investments being made faster than planned at the beginning of the year.
The explanation to your question regarding the West Block is this. At the beginning of 2013-14, we expected 30% of the work to be completed. By the end of the year, however, 34% of the work had been completed. So the cost did not go up; the work simply progressed more quickly than expected.