Thank you for the question.
We bought the campus nearly three years ago. The price was extremely low, so it was an excellent deal. We were also able to save money with the acquisition of the campus. Employees covered by 40 or so leases in and around Ottawa are going to be consolidated in that space. Over a 25-year period, we will save $750 million, which is very significant. The work to fit up the offices is currently under way so the Department of National Defence can move in.
The move will happen in three phases. The first wave of employees to move in will begin officially in December 2015 and continue through June 2016. Between 3,000 and 3,500 people will move into the campus. So the first phase of the move will begin at the end of 2015.
The second phase will start a year and a half later, with another 3,000 people moving to the campus. The third phase will happen in 2019, at which point, 8,500 people will be at the campus.
The fit-up work is happening as we speak and is on schedule. You will start to see more cars in the parking lot beginning in December 2015, with the first wave of employees moving in.