Thank you very much for the question.
In fact, a lot of that is laid out in the report on plans and priorities.
Let me start with the West Block rehabilitation. We're now about 72% complete. Our expectation is that it would be completed by March 2016.
As you are aware, I'm sure, since it may have disrupted some of your operations, we have been undertaking the evacuation activities as the first part of establishing a new visitor welcome centre. That work is also scheduled for completion in March 2016.
Similarly, for the Wellington Building rehabilitation, the fit-up and the installation of the building is about 92% complete. Again, we'll be ready next year.
We've started work on the Government Conference Centre, which includes fit-up, design, and the beginning of some of the interior work. As you're aware, that will become the temporary home of the Senate. Again, we're expecting that to be finished in 2016.
The final part is the East Block exterior rehabilitation. We expect it to be about 15% complete by March 2016.
We're making good progress on all of them. The various estimates in front of you reflect the funding for those projects.