As Mr. Pagan said, the immediate lesson is that we need to give the Receiver General and CFMRS at least four to eight months—and probably closer to eight months—in lead time for them to be able to basically build enough workarounds to let their system accommodate a few extra departments. If we go much past that, the RG has only flagged that it will be costly and effort-intensive. We haven't actually said what it's going to be, although it's in all departments. Until we give them what the upper limit is, they can't give us a complete cost.