Thank you, Mr. Chair.
Thank you, Mr. Pagan and everyone, for being with us this afternoon.
I want to talk a little bit about the Gordie Howe bridge, because it's important for where I come from, Newmarket—Aurora. Obviously, auto sector manufacturing is very important. Much of the trade that crosses the border either originates or ends up near that part of the province of Ontario.
The supplementaries are $283.6 million, I think. Why is this number in the supplementaries, and what's changed that this wasn't in the main estimates? This project, of course, has been ongoing for a long time, and it's really starting to pick up speed now. Some hurdles, such as litigation, have now been removed. Construction is now under way or very close to being under way. Was this a timing thing, or was the cash flow not there to start the construction?