Although we went live with that first grouping to keep the rollout tight and we couldn't explore a variety of potential issues, all departments joined us during our testing phase. We had a 15-month testing phase and all 101 departments.... We had a variation of departments that came in to test with us. The 34 departments did include the vast majority of the automated rules that we had in Phoenix. That was what made them so attractive to go live with. So the 80,000 business rules we programmed into the system were almost entirely used up during that rollout. Nothing new was added to Phoenix in the second rollout. It's the same software, only rolled out twice.
On July 28th, 2016. See this statement in context.