We did what's called a sensitivity analysis to see how different scenarios would affect the cost estimates. We came to the conclusion that one year of delay would cost $2.3 billion. If there were a two-year delay, it would cost an additional $4.8 billion. This is due to the fact that costs are being pushed over a total horizon of about 20 years.