Thank you for the question.
In terms of the first multi-purpose vessel that will be delivered, we expect it to be in service in 2028‑2029. We are currently in the design stage.
We won't be into a contract for the actual cutting of steel for that ship before probably 2025 or 2026.
With respect to the budget, I would offer you the same answer that we have for some of the other projects we have out there, like the program icebreakers and the polar icebreakers. It's not that we don't or won't make those budgets public, but until such time as we actually get into contract, to put those budgets out in the public domain would remove some of the leverage we have in terms of contract negotiations.
We look forward to making those transparent and public, and we will do so at an appropriate time.