If I could respond, we did look at the timeline, but, more importantly, we saw zero evidence of any indication that there was a discussion around the changing of resources that weren't in the bid or an explanation of why someone might be available. We were looking for any evidence that would show that the name of the individual who was initially proposed was no longer available for whatever reason, but there was nothing. There were zero emails back and forth between the technical authority, the business owner at the CBSA, and the supplier themselves.
On January 31st, 2024. See this statement in context.