Thank you for the question.
As it was confirmed last week, I think by the deputy minister of PSPC, these concerns were raised at the director general level within the information, science and technology branch. It is unfortunate that they weren't raised at a wider level. I, as the chief financial officer, did not receive any concerns.
I think this is one of the key lessons learned. This is the reason why, in the new code improvement plan, we've instigated the executive procurement review committee, which will allow us to scrutinize all contracts and all task authorizations above $40,000. This will provide the second line of defence and allow us to do that.