Okay.
What I can't understand is the cost. What we heard from Mr. Gallivan is $370 million, but what we've also heard at committee is that you've spent $438 million. These two numbers are very inconsistent.
What actually concerns me the most is this: In a transition document prepared for the VP of the CBSA on July 31, 2021, it says that the costs are $371.5 million. Interestingly enough, nothing in the estimates or anything else adds up to that at that time point. In fact, you signed a contract on October 6, 2021, for $322,125,778.
Is this contract a result of verbal approvals that were given to Deloitte to do work and you had to then prepare a new contract with Deloitte?