Let's talk about the speed with which this application was developed. We'll get to the complexities in a minute.
If I take 18 months, and I either use 21 working days or 30 working days divided by the 70 versions that were developed, if I'm using 30 days, it will end up about seven days per version that was developed, and if I use 21 days, it will be five and a half business days to develop.
In your testimony, in your response to one of my colleagues, you talked about each version, with the complexity and with the complete testing, taking about a week. Am I right to say that, sir?