That was the largest delay—the fact that they were at the table for $75,000 a door and literally over a week, it was clawed back and we were told the fund was out of money and it's now $25,000 a door, which made it not feasible.
A couple of years of political advocacy and work on the project and CMHC is back to the table for $75,000 a door, so we are proceeding again.
There are certainly delays in the process, and I appreciate some initiatives that have been taken to speed it up. I understand CMHC is now aiming for a 60-day underwriting time frame as opposed to what was previously six months. That's a very positive movement.
We do a lot of work directly with the City of Hamilton trying to expedite and make more efficient the municipal approval processes.