In a limited way, for our first plant, we needed to invest about $50 million, and the second plant would be much larger capacity. We wanted to go from 2,500 units per year to 20,000 units per year, and that would be north of $100 million.
The problem with the investment is the fact that every capital project in the development industry is funded by one owner, and that owner wants to build 100 units of housing pro forma, and that developer cannot afford to invest in manufacturing equipment on top of that. That manufacturing equipment needs to be amortized by 1,000 units of housing.