To your point, is it realistic to think that we could meet that 2035 target?
In Ontario itself, the Ontario electricity system operator says that to get to a net-zero carbon grid in Ontario, it will cost us $400 billion over 25 years. Is that even achievable? That's to take us from 42,000 megawatts to 88,000 megawatts in 25 years. That will be a daunting task. I think they say that we'll need about six times the 14,000 workers that exist for infrastructure today to simply get there.