With respect to the work plan, there are a couple of issues we're working on at the moment. I think we're going to have to get together as a subcommittee.
The first—and this has an influence on the analysts' work—is how big a document we want to produce at the end. There's a big difference between 10,000 pages and 20,000 pages. That's something we need to decide, because that has an influence on how much time they need at the back end of this to prepare that report.
Then another factor is the translation. The translation services are probably the commodity most in demand at the moment, and that also can back us up as well. That's why we haven't quite nailed down a firm, predictable work plan at the moment. It's because we're having to deal with that. I will be asking the subcommittee to talk about this, because we need to figure that out.
Then we may be in a better position to put together that work plan that you're looking at, but please bear with us as we try to answer a couple of questions before that so that we're in a better position to put out that work plan.