There have been attempts around the edges to make the process faster. For example, we shaved a little off the amount of time given for the project definition work. But even within industry, there is concern that if they try to shorten timelines too much, they won't have sufficient time to pull their teams together, do the work that's required, and deliver a quality product. So we think the timelines that are out there right now are agreeable not only to us from a procurement perspective and from a delivery of product perspective, but also to industry.