I can't talk about the audits that are ongoing, but I'm sure we will look at that question. We looked at the CF-18s and found that actually the timeline was extremely long—14 years, I believe. We tried to see why, and there were a number of issues. One was funding throughout the process—the difficulty with the parliamentary process of voting funds year by year. You start into these projects, and you have no certainty that the funds will be available to you in succeeding years, so you have to go back constantly with funding proposals. Those questions, I know, have come up. We will see in these future audits if they come up again.
On June 1st, 2009. See this statement in context.